15.1 C
Tura

Crucial bridge restored in record 58 days in Kuring Kumey in Arunachal Pradesh

Must read

DIBRUGARH, Aug 28: Kurung Kumey district of Arunachal Pradesh was the worst hit district in the entire state due to heavy rains, massive landslides and mudslides.

Several roads, culverts and RCC bridges were washed out due to nature’s fury.

A major bridge over the Kurung bridge was washed away due to the heavy impact of floods on June 30, thereby cutting off road communication to the district with the rest of the world.

At this point of time despite challenges on various fronts including inclement weather, the restoration work began under the leadership of Deputy Commissioner Vishaka Yadav.

Multiple agencies like the NHIDCL, RWD, BRO, DDMO, district administration and private contractors firms were engaged in the restoration work.

At this point of time Chief Minister Pema Khandu extended his helping hand by releasing adequate funds for early restoration of various restoration work in the district.

Advertisement

On Wednesday, due to all these efforts and assistance extended by the local public, the bridge was re-opened, bringing smiles back to people of the district.

Such a important bridge – since it is strategically important for movement of troops and other para military forces to the forward posts of the LAC – getting completed with 58 days is a record in the entire state.

Also Read: Nagaland sets 72-hr deadline for NHIDCL to clear debris on NH 29

Also Watch

Find latest news from every corner of Northeast India at hubnetwork.in, your online source for breaking news, video coverage.

Also, Follow us on-

Twitter-twitter.com/nemediahub

Youtube channel- www.youtube.com/@NortheastMediaHub2020

Instagram- www.instagram.com/ne_media_hub

Download our app from playstore – Northeast Media Hub

More articles

-->
-->

Latest article