Completion of new Meghalaya Assembly building set for delay due to ‘absence’ of labourers

Must read

Shillong, July 26: The ongoing construction of the new building of the Meghalaya Legislative Assembly has been affected to a great extent due to the “absence” of the labourers.

Assembly Speaker Thomas A Sangma on Friday said, “I have been trying to ensure that the progress of work is good enough and in fact I had also made a surprise visit yesterday and I am happy the progress is going okay and smoothly.”

“However, I think because of the recent (happenings), some of the labourers were absent. We were supposed to have 200 workforce but I could see there were only around 50-60 labourers. So that is hampering the progress of the work,” he added.

Advertisement

Asked if the ongoing checks carried out by pressure groups against undocumented migrant workers have affected this landmark project, the Speaker however said, “I don’t know, I will not say anything about it but the workforce is very less but the progress is okay. At this pace I don’t think we will be able to finish within the timeline that was given.”

He informed that 95-96% of the work has been completed in regards to the left wing and right wing portion of the new building.

According to him, so far there has been no cost escalation and that whatever was revised still stands.

Read: Meghalaya Assembly to convene Autumn session from August 23

WATCH:

Find latest news from every corner of Northeast India at hubnetwork.in, your online source for breaking news, video coverage.

Also, Follow us on-

Twitter-twitter.com/nemediahub

Youtube channel- www.youtube.com/@NortheastMediaHub2020

Instagram- www.instagram.com/ne_media_hub

More articles

-->
-->

Latest article