Govt fast-tracks Tura Medical College, aims completion by 2026-27

Must read

Shillong, March 12: Health Minister Ampareen Lyngdoh on Wednesday said the government is leaving no stone unturned to make the Tura Government Medical College functional at the earliest.

Replying in the Assembly during the question hour, Lyngdoh said steps are being taken to fast track the completion of the project.

Advertisement

“Yes, this project is also close to our hearts…and we will leave no stone unturned to ensure (target to complete it) by 2026-27 actually becomes a reality,”she assured.

The minister also informed that the government is calling the National Medical Council (NMC) for inspection.

Advertisement

She said the government is working to increase additional 180 beds to achieve 400 beds as per NMC norms.

To a question raised by Leader of Opposition Mukul Sangma, Lyngdoh said that the status of Tura government medical college is 75%.

Advertisement

The total area of land donation by the clan for the project is 99.00 acres.

“The total amount of money sanctioned  by the government of India (GoI) for the project till date is Rs 170.10 crore. The total amount of money released to the PMC till date is Rs 185.65 crore. The total amount of money released to the contractor for the PMC till date is Rs 178.66 crore,” she informed.

Read: Over 5.32 Lakh households in Meghalaya get tap connections under JJM

WATCH:

Find latest news from every corner of Northeast India at hubnetwork.in, your online source for breaking news, video coverage.

Also, Follow us on-

Twitter-twitter.com/nemediahub

Youtube channel- www.youtube.com/@NortheastMediaHub2020

Instagram- www.instagram.com/ne_media_hub

Download our app from playstore – Northeast Media Hub

More articles

-->
-->

Latest article