NHAI gets deadline to complete Jowai-Ratacherra road works

Must read

Shillong, Feb 5: The Meghalaya High Court has directed the National Highways Authority of India (NHAI) to file an affidavit confirming completion of the Jowai-Ratacherra road construction by February 24.

The order was passed by the division bench headed by  Justice Revati Mohite Dere and Justice W Diengdoh on Wednesday after examining status report submitted by the NHAI in regards to a PIL filed by (deceased) Kynjaimon Amse.

The NHAI has stated in its report, “The main carriageway of the subject stretch, i.e., from Jowai to Ratacherra section stands completed. However, in order to address the recurring issue of landslides at certain vulnerable locations, a separate and independent contract has been awarded for slope protection and allied works at seven vulnerable locations along the Jowai-Ratacherra section…”

NHAI’s counsel assured the court that the remaining patches, including culvert work at Km 105, will be completed within two weeks.

The bench accordingly directed NHAI to file an affidavit confirming completion of the road construction by February 24.

Also ReadBreak-in at KHADC, police on the hunt for culprits

Also Watch

Find latest news from every corner of Northeast India at hubnetwork.in, your online source for breaking news, video coverage.

Also, Follow us on

Twitter-twitter.com/nemediahub

Youtube channel- www.youtube.com/@NortheastMediaHub2020

Instagram- www.instagram.com/ne_media_hub

Download our app from playstore – Northeast Media Hub

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

The reCAPTCHA verification period has expired. Please reload the page.

-->
-->

Latest article